April 2021: Focus of Work Begins to Shift Inside
Focus of Work Begins to Shift Inside:
Construction Progress Toward Completion: 62%
Days Until Start of Classes in New Campus: 254
YIS2C Capital Campaign Progress: 9.8%
The focus of construction activity has begun to shift indoors, with the framing and drywalling of classrooms, offices and other interior rooms well advanced in the North Building, and also getting under way in the South Building.
Read MoreConstruction Progress Toward Completion: 62%
Days Until Start of Classes in New Campus: 254
YIS2C Capital Campaign Progress: 9.8%
The focus of construction activity has begun to shift indoors, with the framing and drywalling of classrooms, offices and other interior rooms well advanced in the North Building, and also getting under way in the South Building.